Repairing Cotuit’s Town Dock and Restoring Little River

An update on the status of the town dock which has been closed to vehicles since the fall of 2021.

Last fall the town banned vehicles from driving onto town dock — a traditional use for loading and unloading commercial fish catches, refueling the county dredge, and the rigging and unrigging of dozens of sailboats. Cars, pickup trucks, crane trucks — all have been a familiar sight on the century old pier since it was first built in the 1920s.

That dock has been rebuilt or repaired several times over the years, extended in the 1970s from its original square configuration to include the four dinghy floats and an L-shaped extension that extended it another 50 feet into Cotuit Bay. When a permit was requested to allow a fuel truck to refuel a vessel from the dock the Cotuit fire chief and harbormaster discovered the pier was rated with a carrying capacity of only 10,000 pounds, yet has been used by trucks weighing three times that amount.

So the dock was closed to vehicles — its entrance blocked off by a cube of concrete that has been replaced with a metal post that can be unlocked and folded flat — and remains closed. The impact will first be felt this spring when Murray Marine needs to swap the mooring field’s winter sticks with mooring balls and sailboat masts need to be stepped with a boom truck.

Last week the town released its FY2023 capital budget and FY2023-2027 capital improvement plan. It’s a big document with a list of all the projects pending in the town — from bathrooms in town’s offices to repaving beach parking lots.

There are a number of Cotuit projects of interest. Foremost being repairs to the town dock. For those too lazy to download the big PDF (here). I’ll summarize a few.

Cotuit Projects

Cotuit Town Down Design & Permitting: p. 217, MEA-23. Listed as the second priority in the Marine & Environmental Affairs list of 18 projects. The request is for $70,000 to design improvements to the existing dock and “evaluate it to confirm that a retrofit of the existing structure is feasible (i.e. increase pier cap sizings and decking. If the current dock structure cannot be retrofit to accommodate a load rating increase, then additional funding will be required for the design and permitting of a complete reconstruction of the dock.”

Repair work or reconstruction would happen in 2024, costs to be determined by the results of the survey and redesign work.

from the Barnstable FY2023-2027 Capital Improvement Plan

Evaluation of Little River Fish Passage Restoration

Little River connects Lovell’s Pond to Cotuit Bay, where it empties into the harbor at Handy Point. It is a major watershed for three Bays, one of three important freshwater contributors (along with the Mills River to the east and the Santuit River to the west). A historic herring run and important habitat for other anadromous species including the American Eel, Rainbow Smelt, winter flounder, and Sea Run Brown Trout, Little River has been severely compromised by various man-made obstacles along its short course from its headwaters at the southeast corner of Lovell’s Pond, under Route 28 near the offices of the Cotuit Water Company, and through the woods around Sampson Mill Road, south parallel to Putnam Avenue, emerging in a series of man made culverts and ponds created by a developer in the 1960s before flowing under Putnam Ave at the base of the old Green Acres curve at Bell Farm, and then through the woods of the glacial valley to the east of Mosswood Cemetery and under Old Post Road where it opens up to the saltmarsh that divides the Little River neighborhood and Handy point from the rest of Cotuit.

This project– MEA-23 — is ranked 7th in priority of the Marine and Environmental Affair’s list of 18 projects and requests $100,000 to perform:

“A comprehensive assessment of restoring fish passage in Little River. Little River was historically a vibrant herring run with fish traveling to spawn in Lovell’s Pond in Cotuit. However, current conditions prohibit the migration of fish into the herring run at multiple locations….”

Deferred Marine & Environmental Affairs General Fund Projects, 2023 CIP p 223
From p.224 of the Town of Barnstable FY2023-2027 Capital Improvement Plan

Other projects of interest (to me at least) include:

West Bay Breakwater improvements to put new boulders on the Wianno Cut jetties and repair the navigation light at the end of the eastern jetty. That project carries a $5.150 million price tag

Channel Dredging: Cotuit Bay is listed in 2024 for a “Cotuit Bay Embayment Channel 7′ section ($75,000). The entrance to Osterville at West Bay and the Seapuit River is scheduled for a big dredging in 2027: “West Bay Outer Entrance $150,000), West Bay Inner Entrance Channel – Lower Reach ($1,000,000), Seapuit River Channel ($360,000), project management contingency ($100,000)

Author: David Churbuck

Cape Codder with an itch to write

Leave a ReplyCancel reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Discover more from Churbuck.com

Subscribe now to keep reading and get access to the full archive.

Continue reading

Exit mobile version
%%footer%%